Bylaw

Town bylaw 1026: Bylaw No. 1026, 2022 Schedule E - Building Permits

What this bylaw is for

Bylaw No. 1026, 2022 Schedule E - Building Permits is a Town of Princeton bylaw filed under Bylaws / FEES & CHARGES AND AMENDMENTS. The published number is 1026. Town of Princeton Fees and Charges Bylaw 1026, 2022 Page 8 SCHEDULE “E” - Building Permits E01 – Building permit plan processing fee levied as the rate for a building permit processing fee as detailed in Section 10.7 of the Town of Princeton Building Bylaw No. 976, 2020. Rate is collected per permit. The amount collected is non-refundable once the building permit has been issued. E02 - Building Permit Fee levied as the rate for a building permit fee as detailed in Section 10.7 of the Town of Princeton Building Bylaw No. 976, 2020. Rate is collected as a measure of the charge per $1,000 of building permit value using the appendix listed in Schedule “E” of this bylaw. The two charges in E01 and E02 satisfy the building permit fee in Section 10.7 of the the Town of Princeton Building Bylaw No. 976, 2020. The amount collected is non-refundable once the building permit has been issued. E03…

The bylaw text

Extracted from the published PDF for reading. This is not a substitute for the official file on CivicWeb. No OCR — scanned pages may be empty.

Town of Princeton Fees and Charges Bylaw 1026, 2022 Page 8

SCHEDULE “E” - Building Permits E01 – Building permit plan processing fee levied as the rate for a building permit processing fee as detailed in

Section 10.7 of the Town of Princeton Building Bylaw No. 976, 2020. Rate is collected per permit. The amount

collected is non-refundable once the building permit has been issued. E02 - Building Permit Fee levied as the rate for a building permit fee as detailed in Section 10.7 of the Town of Princeton Building Bylaw No. 976, 2020. Rate is collected as a measure of the charge per $1,000 of building permit value using the appendix listed in Schedule “E” of this bylaw. The two charges in E01 and E02 satisfy the building permit fee in Section 10.7 of the the Town of Princeton Building Bylaw No. 976, 2020. The amount collected is non-refundable once the building permit has been issued. E03 - Building Relocation Fee levied as the rate for a building permit fee as detailed in Section 10.7 of the Town of Princeton Building Bylaw No. 976, 2020. Rate is collected as a measure of the charge per $1,000 of building permit value using the appendix listed in Schedule “E” of this bylaw. Only the larger value of E01 or E03 is charged as the cost of the building permit. E04 - Demolition Permit Fee levied as the rate for a building permit fee as detailed in Section 10.7 of the Town of Princeton Building Bylaw No. 976, 2020. Rate is charged per permit. E05 – Voluntary reinspection fee levied as the rate for a building permit fee as detailed in Section 10.44 of the Town of Princeton Building Bylaw No. 976, 2020. Rate is charged per individual inspection as detailed in Section 10.44. E06 -. Permit extension fee levied as the rate for a building permit fee as detailed in Section 10.26 of the Town of Princeton Building Bylaw No. 976, 2020. Rate is charged per approved transfer. This fee is non-refundable once the transfer is granted and registered.

Table A-1 Proposed Construction Value per square meter Value per square foot One storey on a crawl space $1,238 $115 One storey on an unfinished basement $1,346 $125 One storey on a finished basement $1,507 $140 Additional storey(ies) $484 $45 Enclosed structure or garage $323 $30 Sundeck $269 $25 Roof only $161 $15 Unenclosed structure or carport $269 $25 Pool $377 $35 Foundation (crawlspace) $161 $15 Foundation (unfinished basement) $269 $25 Foundation (finished basement) $377 $35

Rates as at September 1, 2022 or annual rate in 2022 Rates as at September 1, 2023 or annual rate in 2023 Rates as at September 1, 2024 or annual rate in 2024 Rates as at September 1, 2025 or annual rate in 2025 Rates as at September 1, 2026 or annual rate in 2026 E01 Building permit plan processing fee 160.00$ 170.00$ 175.00$ 185.00$ 195.00$ E02 Building permit fee 10.80 $ 11.40$ 12.00$ 12.60$ 13.20$ E03 Building relocation permit 10.80 $ 11.40$ 12.00$ 12.60$ 13.20$ E04 Demolition permit 160.00 $ 170.00$ 175.00$ 185.00$ 195.00$ E05 Voluntary reinspection fee 110.00 $ 115.00$ 120.00$ 125.00$ 130.00$ E06 Permit extension fee 110.00 $ 115.00$ 120.00$ 125.00$ 130.00$ E07 Permit transfer fee 110.00 $ 115.00$ 120.00$ 125.00$ 130.00$

Sources

  1. Bylaw No. 1026, 2022 Schedule E - Building Permits

Generated 2026-09-20T01:14:21.120416+00:00 · model fallback